In the past period, the GMM MFF has adopted a number of documents for Tranche 3 that are important for market parties. Which ones are they?
Modified Entry Documentation by RFC-013
On 28March 2024, the RFC-013-A2.0-TR3 ‘Formules reconciliëren TMT en SMA’ (‘Formulas reconcile TMT and SMA’) was approved. As a result of this Request for Change, some changes had to be made to the issue documents IC257 ‘Settlement GV Telemetrie Elektriciteit’ (‘Settlement GV Telemetry Electricity’) version 2.0 and IC275 ‘Settlement SMA’ version 2.0. The amended issue documents have been established. You can find them on mijnMFFBAS: ‘Release’, ‘Tranche 3 A2.0’, folder ‘1. Topics, BRS, MSP‘.
2 Requests for Change (RFC’s)
For Tranche 3, 2 RFC’s have also been established:
- RFC-019-A2.0-TR3 ‘TS044 in scope Tranche 3’. On 8 December 2023, the Portfolio Steering Committee (PFSG) adopted a topic: TS044 (IC285) Reclamatieproces maandmeetgegevens, volumes voor reconciliatie en reconciliatieresultaten TMT en SMA’ (‘Monthly measurement data complaint process, reconciliation volumes and TMT and SMA reconciliation results’). The complaint processes in TS044 relate to processes from Tranche 3. With the RFC, TS044 will be included in the go live of Tranche 3 on 1 January 2025. In this way, market parties can implement and deploy the complaints described in the topic in a timely manner from the implementation of issues IC257 and IC275 from Tranche 3. The exchange of complaints from TS044 takes place via e-mail.
View topic TS044 on mijnMFFBAS: ‘Release’, ‘Tranche 3 A2.0’, folder ‘1. Topics, BRS, MSP‘. - RFC-021-A2.0 TR3 IC252 ‘ Herplanning T2 Oplevering RNB-functionaliteit maken VVV’ (Rescheduling T2 Delivery RNB functionality make collective settlement request (VVV)’). The distribution system operators have indicated that issue IC252 will be delivered later than in the original milestone planning due to unexpected complexity. As a result, the construction of IC252 is split. The electricity part will be delivered for testing earlier than the gas part. In a 2.0 version, the transition document ‘Implementation scenarios’ will be adapted accordingly. The explanation of the changed schedule can be found in the RFC.
Overview of RFC’s
The following RFC’s have now been established for Tranche 3:
For the contents of the RFC’s, go to mijnMFFBAS: ‘Release’, ‘Tranche 3 A2.0’, folder ‘3. RFC’s‘.
Transition documents
Furthermore, the following 2 documents have been adopted for the transition:
- A2.0 T3 ‘Transitie Implementatiescenario’s’ (‘Transition Implementation Scenarios’) v1.0. This document lists the different scenarios in case not all topics can go live in the go live window. Please note: due to RFC-021, this document will be updated.
- A2.0 T3 ‘Marktimpact Marktpartij Niet Gereed’ (‘Market Impact Market Party Not Ready’) v1.0. In this document, you can read about the consequences for the processes in the chain if the sector goes live on 1 January 2025 but a market party is not ready.
View the two transition documents on mijnMFFBAS: ‘Release’, ‘Tranche 3 A2.0’, folder ‘6. Transitie’.