Planning Tranche 4 and IC280 Light established. Implementation starts on 8 November

On Friday 11 October, the Portfolio Steering Committee (PFSG) established the planning of Tranche 4 of the Allocatie 2.0 programme. The implementation phase will start on 8 November and the go live on 1 May 2026.

 

Topics

For Tranche 4, 3 topics are in scope:

  • TS039-IC283 ‘Restantvolume Configuratie’ (‘Residual Volume Configuration’)
  • TS040-IC258 ‘Slimmemeterallocatie’ (‘Smart Meter Allocation’)
  • TS041-IC247A ‘Optimalisatie meetketen voor kleine aansluitingen (kleinverbruik)’ (‘Optimisation of the measurement chain for small connections (small consumption)’)
Planning

For Tranche 4, the following T-moments have been established:

  • T1: start implementation = 8 November 2024
  • T2′: start of Lead Group Tests = 5 January 2026
  • T2: start of User Acceptance Testing = February 2, 2026
  • Go live = May 1, 2026
Simultaneous release topic TS046-IC280 Light

It is planned to release topic TS046-IC280 Light (Reconciliation messages PRF to XML) simultaneously. But the topic is not part of Tranche 4. For TS046-IC280 Light, this is the planning:

  • T1: start implementation = 8 November 2024
  • T2′: start of Lead Group Tests = 1 September 2025
  • Start Qualifying = December 1, 2025
  • Go live = May 1, 2026
Topic TS045-IC286 out of scope

The topic TS045-IC286 ‘Informatiestroom intervalvolumes per Aansluitpunt’ (‘Information flow interval volumes per Connection Point’) is not yet part of the scope of Tranche 4. The topic depends on a ministerial regulation (MR) under the new Energy Act. The publication of the MR may take so long that this topic can no longer be added to Tranche 4 and may be released separately at a later date.

Flanking topics

The suppliers have expressed their concerns that the scope of Tranche 4 is too narrow to allow the entire measurement and mutation chain for small consumption to function. This requires flanking topics. These topics depend on the Energy Act to be delivered and in particular on the MR. If the flanking topics are established and implemented with delay, this may have consequences for the planning of Tranche 4. In that case, a Request for Change (RFC) may be required.

View the schedule of Tranche 4 and TS046-IC280 Light on mijnMFFBAS. Go to: ‘Release’, ‘Tranche 4 & IC280Light A2.0’, folder ‘4. Projectmanagement’.


 

Contact Become member My MFFBAS Meer

Contact

033 303 7322
vragen@mffbas.nl
Van Asch van Wijckstraat 55
3818 LH Amersfoort
KVK: 84811439
BTW: NL863384183B01
Join us My MFFBAS