On Friday 13 December, the go live of Tranche 3 of Allocatie 2.0 can take place. What does the schedule look like?
Planning: happy flow or fallback
On Friday 13 December 10:00, the Integral Implementation Management Consultation (IISO) will assess whether the acceptance criteria for a successful technical go live have been met. There are then 2 scenarios:
- The acceptance criteria are met. The technical go live will take effect immediately. The functional go live will then take place on Wednesday 1 January 2025.
- The acceptance criteria are not met. The Fallback Plan comes into effect. The IISO postpones the technical go live until at least Monday 16 December 10:00. Where necessary, a new decision-making process will follow on Friday 20 December.
Systems remain available
During the technical and functional go live, you can continue to use the central systems and processes.
Stay informed
We will keep you informed of the progress via our newsletter. The news can also be found on the MFFBAS website. For the transition and fallback documents, go to mijnMFFBAS: ‘Release’, ‘Tranche 3 A2.0’, folder ‘6. Transitie‘.